"How much will it cost to build my house?" is the first question every plot owner in Faisal Hills asks — and the most common reason builds blow their budget is guessing the answer instead of calculating it. Here is a transparent 2026 breakdown of grey structure and finishing costs, with a worked 5 Marla example you can reproduce on our free Construction Cost Calculator.

How much does it cost to build a house in Faisal Hills in 2026?

Short answer: for a standard-quality, double-storey home on a 5 Marla plot with about 85% coverage, expect roughly PKR 11.1 million in construction (grey structure + finishing), excluding land, boundary wall and development charges. Economy finishes cost less; luxury pushes it toward PKR 13.4 million. The figure scales with covered area and finish quality, so let us show the working.

The method: covered area × rate, split into grey and finishing

Construction cost is driven by two things — how much covered area you build, and the per-square-foot rate for your finish quality:

  • Covered area = plot size (sq ft) × coverage % × number of storeys. A 5 Marla plot is 1,125 sq ft (1 Marla = 225 sq ft in the Twin Cities).
  • Grey structure rate covers the frame: foundation, columns, slabs, blockwork, plaster.
  • Finishing rate covers everything you see: flooring, kitchen, baths, doors, paint, electrical and plumbing fixtures.

We quote them separately so you can see exactly where the money goes, and we tie each rate to a named material specification rather than a vague per-Marla rumour.

Worked example: a 5 Marla double-storey home

Take a 5 Marla plot, 85% coverage, 2 storeys, standard quality (grey PKR 2,700/sq ft, finishing PKR 3,100/sq ft):

  1. Plot area = 5 × 225 = 1,125 sq ft
  2. Covered area = 1,125 × 0.85 × 2 = 1,912.5 sq ft
  3. Grey structure = 1,912.5 × 2,700 = PKR 5,163,750
  4. Finishing = 1,912.5 × 3,100 = PKR 5,928,750
  5. Total construction = PKR 11,092,500

Switch to a luxury finish (PKR 7,000/sq ft combined) and the same house costs PKR 13,387,500 — the finish tier alone moves the number by about PKR 2.3 million, which is why quality level matters as much as size.

What the estimate excludes

This is construction only. It does not include the plot price, the boundary wall, development or utility charges, or approval fees. For a guaranteed all-in turnkey price (land + build + finish on a fixed payment plan), see our construction packages — for example the 5 Marla house construction cost in A Block, the 10 Marla house construction cost in B Block, or the full grey-structure and finished-home rates by size in Faisal Hills.

Should you buy a ready house or build your own?

Building gives you control over layout and finish and can be cheaper — but only if the numbers say so. As an example: a ready house at PKR 28 million versus a PKR 9 million plot plus 3,000 sq ft of construction at PKR 5,800/sq ft (PKR 17.4M) totals PKR 26.4 million — building wins by PKR 1.6 million. But raise the covered area to 3,500 sq ft and the build reaches PKR 29.3 million, and buying ready becomes cheaper. Run both paths on our free Buy vs Build tool before you decide.

Check the materials yourself

Because we tie the estimate to named brands at current rates, you can price your own bill of quantities — cement, Grade-60 steel, bricks, sand, crush, tiles and labour — on the free Material Prices sheet and check any contractor's quote line by line.

Get your exact figure on the Construction Cost Calculator, then message our team on WhatsApp for a fixed, itemised quote for your specific plot and design in Faisal Hills or B-17.

Rates are indicative 2026 Twin-Cities estimates and are updated as the market moves; final cost depends on your design, specification and site conditions. Confirm with Al Ammana Developers before budgeting.

Questions & answers

How much does it cost to build a 5 Marla house in Faisal Hills in 2026?+

For a standard-quality double-storey home at ~85% coverage, about PKR 11.1M in construction (grey structure PKR 5.16M + finishing PKR 5.93M), excluding land, boundary wall and development charges. A luxury finish raises it to about PKR 13.4M.

How is construction cost calculated?+

Covered area = plot size (sq ft) × coverage % × storeys; then grey structure = covered area × grey rate, finishing = covered area × finishing rate. For a 5 Marla (1,125 sq ft) plot at 85% over two floors, covered area is 1,912.5 sq ft.

What does the construction estimate exclude?+

It is construction only — it excludes the plot price, boundary wall, development and utility charges, and approval fees. For an all-in turnkey price on a fixed payment plan, see Al Ammana's construction packages.

Is it cheaper to buy a ready house or build my own?+

It depends on the covered area. In our example a PKR 28M ready house versus a PKR 9M plot plus 3,000 sq ft of build (PKR 26.4M) favours building by PKR 1.6M — but at 3,500 sq ft the build reaches PKR 29.3M and buying ready wins.

Build or buy with Al Ammana